Released
Jacqui Blakemore
2 years ago
Thanks for this feedback. We are looking to change how this functionality works when placing orders in an upcoming release.
Jacqui Blakemore changed the status to In Progress
2 years ago
Stuart Friend changed the status to Completed Development
2 years ago
Stuart Friend changed the status to Released
2 years ago
Dan Elwell
2 years ago
When multiple different material configurations are within the material bill if for example we have 1,000m2 of 15mm Soundbloc within the bill made up of some 2400mm boards, some 2700mm and some 3000mm boards if the correct quantity of configuration is not ordered then it moves the cost for this to contingency when it may be that the total 1,000m2 has not been exceeded.
It would be beneficial if materials with configurations are shown on one line with te option to select the configuration when ordering and the m2 or lm of material ordered deducted from the total material allowance.